![]() |
![]() |
![]() |
Home > News > Planned Works Programs
| Electricity Interruptions | Sewer Works | |||||||||||||||||||||||
Electricity supply will be interrupted for upgrading and maintenance at: LeanyerTuesday 2 December, 8.30am - 12.30pm
LeanyerWednesday 3 December, 8.30am - 12.30pm
Howard SpringsThursday 4 December, 9.30am - 1.30 pm
Casuarina Zone Substation Project. Jingili suburban generator commissioning will affect: Jingili, MillnerThursday 4 December, 8.00am - 11.00amAn outage of up to 15 minutes can be expected during these hours.
Lee Point suburban generator commissioning will affect: Lyons, Tiwi, WanguriThursday 4 December, 1.00pm - 4.00pmAn outage of up to 15 minutes can be expected during these hours.
[ back to top ]
Water supply may be interrupted for maintenance works at: PinelandsSaturday 30 November, 9.00 am - 3.00 pm
Valve and fire hydrant maintenance and installation will take place at: Alawa, Moil, Wagaman, Darwin CBDMonday 1 - Friday 5 December
Water Main connection will take place at: ArcherMonday 1 - Friday 5 December
[ back to top ]
Power and Water contractors have commenced works to upgrade the underground high voltage power cables around the Casuarina commercial district. Schedule of works are as follows:
Once trenching is complete high voltage cables will be laid. Works are scheduled to be completed by Wednesday 17 December. Pedestrian and vehicle access throughout these works will be maintained and traffic management signage will be in place. For more information contact the Distribution Develoment Engineer, Christina Camilleri on 8924 5124 or email christina.camilleri@powerwater.com.au. [ back to top ]Works to install a new 4.2km transmission water main at: PalmerstonExpected completion date of January 2009 Howard Springs Road to Temple Terrace Along Temple Terrace from the Stuart Highway to Roystonia Avenue For more information contact the Senior Engineer Infrastructure Development, Daniel Lobley, on 8985 7139 or email daniel.lobley@powerwater.com.au. [ back to top ] If we know about it, we can fix it.We’re working hard to keep you safe. This includes regular maintenance on all Power and Water Corporation assets and conducting a safety audit on our 20 000 streetlights, and all our power poles. If you see something that looks out of place call us on 1800 245 092, email customerservice@powerwater.com.au or complete our feedback form.
|
Access chamber maintenance works will take place at:
Coconut Grove, Wagaman, Moil, Malak, Alawa, BakewellMonday 1 - Friday 5 December
CCTV investigation and relining work will take place at: NightcliffMonday 1 - Friday 5 December
Descaling line work will be carried out at: Rapid Creek, Nightcliff, Stuart Park, Coconut GroveMonday 1 - Friday 5 December
Pipe relining work will be carried out at: The NarrowsMonday 1 - Friday 5 December
[ back to top ]
We will be trimming trees at: Ludmilla, Winnellie, Stuart Park, ParapMonday 1 - Friday 5 December
HerbertMonday 1 - Friday 5 December
Alice Springs - BraitlingMonday 1 - Friday 5 December
[ back to top ]
November 2008Civil Works along street (comprising excavation, laying of conduits and concrete footpaths) Rapid Creek
Installation of electrical cables (both under new footpath and into properties), distribution pillars, streetlight columns and substations. Rapid Creek
[ back to top ] Affected residents will be advised shortly. Undergrounding works have now commenced in Rapid Creek in SP4 (Areas A15-A19). This area is bordered by Fox Crescent/Rossiter Street/Rapid Creek Road/Casuarina Drive/Ternau Street. Affected residents will be notified accordingly prior to the commencement of works View the Areas Maps Undergrounding the House Service A new underground service will be installed into each property (if not already underground) by boring two conduits to the existing supply point (this is the meterbox in most cases). Cables are then installed into the conduits until they are terminated in readiness for the final changeover to underground supply. Electrical Works Ground Penetrating Radar What about streetlights? As most of the streetlights are on the power poles that will be removed, new streetlighting will be installed to meet the Australian Standard. Where possible, it is planned to place the new streetlight columns at the common boundary of properties. Who pays for underground power? Undergrounding the power supply is a Northern Territory Government initiative and the government is directly funding the majority of the works. Power and Water is funding the remainder on a commercial basis. Improving ReliabilityOn average, areas of Darwin already supplied by underground power have less than one quarter of the power interruptions than the areas supplied by overhead powerlines. Undergrounding the power will greatly reduce the risk of another cyclone devastating Darwin’s electricity distribution network. Managing Contractor:Nilsen Electric For more information, contact the |
|||||||||||||||||||||||