Stuart Highway / Telegraph Terrace resurfacing works
Project Status: CompletedOverview
Stage 2- Stuart Highway / Telegraph Terrace – Road Closure
Resurfacing works will take place on the Stuart Highway between Wills Terrace and Stott Terrace (including Larapinta Drive intersection) and; Stott Terrace and Traeger Avenue from Thursday 17 May 2012.
This project is part of the Australian Government’s Strengthening and Widening program, to provide improved roads.
Impact
The majority of works will occur at night to minimise disruption to traffic, and will take approximately three weeks to complete.
Works taking place on the inbound and outbound lanes, with changes to the flow of traffic. Detours will be in place during this time.
In the interest of safety, traffic management will be present and motorists are advised to heed all traffic devices and speed limits in place around the road works.
Commencement of works
Thursday 17 May
Completion of works
Thursday 7 June
Contacts
| Further Information: | Andrew Batson Senior Project Manager 08 8999 4873 |
| Email Address: | andrew.batson@nt.gov.au |